Roads23HO0152

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, DALAGUETE-MANTALONGON-BADIAN RD (BADIAN SIDE) - K0106

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, DALAGUETE-MANTALONGON-BADIAN RD (BADIAN SIDE) - K0106 is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱72,372,953.76. Status: Reported complete (DPWH). Contractor on record: GICAR CONST INC 12624. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Wall Structures at Sitio Aransana - Sitio Sulok (Right Side Upstream), Brgy. Mindanao, Malabuyoc, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 7th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱72,372,953.76

Progress

Reported complete (DPWH)

Start Date

March 16, 2023

Target End

December 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.