Buildings and Facilities16GG0097

CONSTRUCTION OF ONE (1) STOREY, ONE (1) UNIT (PROVISION OF TECHVOC WORKSHOP BUILDINGS/LABORATORIES FOR SENIOR HIGH SCHOOL)-BATCH 10, LEON MEDIANA NATIONAL HIGH SCHOOL, CALINOG, ILOILO

CONSTRUCTION OF ONE (1) STOREY, ONE (1) UNIT (PROVISION OF TECHVOC WORKSHOP BUILDINGS/LABORATORIES FOR SENIOR HIGH SCHOOL)-BATCH 10, LEON MEDIANA NATIONAL HIGH SCHOOL, CALINOG, ILOILO is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱2,380,197.31. Status: Reported complete (DPWH). Contractor on record: 5'S CONST. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Jarao Flood Control Project, Particion, Guimbal, Iloilo
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-16-0038902

₱360,000,000.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱2,380,197.31

Progress

Reported complete (DPWH)

Start Date

October 13, 2016

Target End

January 10, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.