Buildings and Facilities25K00149

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BAYANG, LANAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BAYANG, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱7,378,092.96. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: XD DEVELOPERS 44723. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱7,378,092.96

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 3, 2025

Target End

August 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.