Roads23IA0013

REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL ROAD - K1039+020 - K1039+170 (124°21'38,11°38'52 TO 124°21'40, 11°38'56), BRGY. MATANGO, ALMERIA, BILIRAN

REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL ROAD - K1039+020 - K1039+170 (124°21'38,11°38'52 TO 124°21'40, 11°38'56), BRGY. MATANGO, ALMERIA, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱48,304,605.93. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagombong Flood Control along Biliran Circumferential Road, Phase 5, Almeria, Biliran
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Biliran DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱48,304,605.93

Progress

Reported complete (DPWH)

Start Date

February 8, 2023

Target End

September 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.