Buildings and Facilities20EB0132

CONSTRUCTION OF 2STY-4CL, MAPAYA II ES, SAN JOSE, OCCIDENTAL MINDORO

CONSTRUCTION OF 2STY-4CL, MAPAYA II ES, SAN JOSE, OCCIDENTAL MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱11,538,017.69. Status: Reported complete (DPWH). Contractor on record: AMM CONST AND CONST SUPPLIES 43357. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,538,017.69

Progress

Reported complete (DPWH)

Start Date

October 1, 2020

Target End

March 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.