Flood Control and Drainage25CL0082

CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 6, SANTA CRUZ, ZAMBALES

CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 6, SANTA CRUZ, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱95,100,665.28. Status: Past target date (DPWH On-Going). Contractor on record: S-ANG CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Stabilization Structure along Gabor River, Phase 1, San Felipe, Zambales
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zambales 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

54 projects · ₱3.8B total · 0 flags

4. Implementation

Contract Amount

₱95,100,665.28

Progress

Past target date (DPWH On-Going)

Start Date

March 4, 2025

Target End

January 27, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.