Buildings and Facilities24J00266

CONSTRUCTION OF 2-STOREY 10-CLASSROOM, SCHOOL BUILDING AT SULTAN JAMALUL KIRAM CENTRAL HIGH SCHOOL, BRGY. LAUM MAIMBUNG, SULU

CONSTRUCTION OF 2-STOREY 10-CLASSROOM, SCHOOL BUILDING AT SULTAN JAMALUL KIRAM CENTRAL HIGH SCHOOL, BRGY. LAUM MAIMBUNG, SULU is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱39,794,998.09. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: AL-SADIK CONST & ENT INC 36740. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱39,794,998.09

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

January 7, 2025

Target End

June 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.