Water Provision and Storage23LA0096

CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY NEW BARILI, MUNICIPALITY OF MACO, PROVINCE OF DAVAO DE ORO

CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY NEW BARILI, MUNICIPALITY OF MACO, PROVINCE OF DAVAO DE ORO is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱9,798,284.32. Status: Past target date (DPWH On-Going). Contractor on record: AGONG BUILDERS AND CONST SUPPLY INC 40494. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tagum - Libuganon River, Talomo, Sto. Tomas, Davao del Norte (Phase 1)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Davao de Oro 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,798,284.32

Progress

Past target date (DPWH On-Going)

Start Date

November 24, 2023

Target End

July 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.