Roads20K00221

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAYRE HIGHWAY PARALLEL ROAD I (LIBONA - MANOLO FORTICH - IMPASUG-ONG SECTION), PACKAGE 11, BUKIDNON

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAYRE HIGHWAY PARALLEL ROAD I (LIBONA - MANOLO FORTICH - IMPASUG-ONG SECTION), PACKAGE 11, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱109,924,250.88. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱109,924,250.88

Progress

Reported complete (DPWH)

Start Date

December 7, 2020

Target End

January 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.