Rehabilitation / Major Repair of Flood Control Structure22FA0058

Rehabilitation of Calbayog River Wall, Malilipot, Albay

Rehabilitation of Calbayog River Wall, Malilipot, Albay is a DPWH-tracked public work in MALILIPOT (ALBAY), ALBAY, Region V. Reported contract value: ₱24,500,000.00. Status: Reported complete (DPWH). Contractor on record: DSB CONST & SUPPLY INC FORMERLY: DSB CO. Figures trace to sumbong.

MALILIPOT (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱44,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Bulawan Flood Control, San Francisco Section, Malilipot, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003098

₱142,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003135

₱141,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003044

₱135,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003055

₱46,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱24,500,000.00

Progress

Reported complete (DPWH)

Start Date

May 30, 2022

Target End

November 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.