Buildings and Facilities19AJ0098

CONSTRUCTION (COMPLETION) OF PANGASINAN IV DISTRICT ENGINEERING OFFICE BUILDING, TULIAO, STA. BARBARA, PANGASINAN

CONSTRUCTION (COMPLETION) OF PANGASINAN IV DISTRICT ENGINEERING OFFICE BUILDING, TULIAO, STA. BARBARA, PANGASINAN is a DPWH-tracked public work in Pangasinan 4th DEO, Region I. Reported contract value: ₱5,835,672.82. Status: Reported complete (DPWH). Contractor on record: JEUSMACK BUILDERS. Figures trace to dpwh.

Pangasinan 4th DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,835,672.82

Progress

Reported complete (DPWH)

Start Date

August 6, 2019

Target End

January 2, 2020

5. Audit