Buildings and Facilities24OD0203

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO GITNA, BARANGAY 166, CALOOCAN CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO GITNA, BARANGAY 166, CALOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱4,894,846.69. Status: Reported complete (DPWH). Contractor on record: EIRISH BUILDERS. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks, Barangay 166, Caloocan City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Metro Manila 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱3.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD,PHASE II,SITIO TALAMSI I-SITIO KAMB

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG. - SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGSS/ FACILITIES - CONST.OF ROAD, PHASE I, SITIO TALAMSI I - SITIO KAM

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), ANGAT, BULACAN

Bulacan 2nd DEO, Region III

2023₱117.5M
Reported complete (DPWH)
No sat.

STATE UNIVERSITIES AND COLLEGES (SUCS)-ESTABLISHMENT AND/OR SUPPORT TO THE COLLEGE OF MEDICINES, SAN RAFAEL CAMPUS-BULACAN STATE UNIVERSITY, SAN RAFAEL, BULACAN, PROVINCE OF BULACAN

Region III, Region III

2024₱98.5M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LONGOS - ZAMORA SECTION, STA. 06+220 - STA. 06+340, MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF SAN JOSE DEL MONTE SCHOOL OF NURSING AND ALLIED HEALTH (PHASE 2), BARANGAY MINUYAN PROPER, CITY OF SAN JOSE DEL MONTE, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.0M
Past target date (DPWH On-Going)
View all 126 projects →

4. Implementation

Contract Amount

₱4,894,846.69

Progress

Reported complete (DPWH)

Start Date

April 26, 2024

Target End

September 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.