Flood Control and Drainage18EA0073

PACKAGE III- A) CONSTRUCTION OF BAMBAN FLOOD CONTROL, BOAC, MARINDUQUE, B) CONSTRUCTION OF POCTOY FL

PACKAGE III- A) CONSTRUCTION OF BAMBAN FLOOD CONTROL, BOAC, MARINDUQUE, B) CONSTRUCTION OF POCTOY FL is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱11,047,292.80. Status: Reported complete (DPWH). Contractor on record: JBERNARDO CONST AND SUPPLY 42108. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,047,292.80

Progress

Reported complete (DPWH)

Start Date

April 2, 2018

Target End

August 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.