Buildings and Facilities25PJ0047

25PJ0047-CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALALUPA, BARANGAY CARAGASAN, ALFONSO LISTA, IFUGAO

25PJ0047-CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALALUPA, BARANGAY CARAGASAN, ALFONSO LISTA, IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱1,979,950.51. Status: Reported complete (DPWH). Contractor on record: MR-G CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Poblacion Pakawit Communal Irrigation System (CIS), Tinoc, Ifugao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ifugao 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

31 projects · ₱144.5M total · 0 flags

Other projects by this contractor

No sat.

23PJ0045: REPAIR/REHABILITATION ANDCONSTRUCTION OF FARM-TO-MARKET ROADS IN DESIGNATED KEY PRODUCTIONAREAS-CONCRETING OF SITIO ALWASA PUMPHOUSE TO FISHPORT, BRGY. STO.DOMINGO FMR, BRGY. STO. DOMINGO, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱11.9M
Reported complete (DPWH)
No sat.

24PJ0044-CONCRETING OF BALANGBANG TO BANAO, FMR, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱9.9M
Reported complete (DPWH)
No sat.

24PJ0045-CONCRETING OF SITIO TAMANG, BRGY. DAMAG FMR BRGY. DAMAG, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱9.9M
Reported complete (DPWH)
No sat.

23PJ0041: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BRGY. UBAO, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱9.9M
Reported complete (DPWH)
No sat.

25PJ0031: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP)-ACCESS ROAD LEADING TO AMMUNG FESTIVAL, YAO JIA XI DRAGON FRUIT FARM, DOMINGO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTIPURPOSE BUILDING IN KILING, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2022₱5.0M
Reported complete (DPWH)
View all 31 projects →

4. Implementation

Contract Amount

₱1,979,950.51

Progress

Reported complete (DPWH)

Start Date

March 10, 2025

Target End

June 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.