Construction of Flood Mitigation Structure23HO0223

Construction of Ylaya Flood Control (Upstream) (Phase II), Ylaya, Dumanjug, Cebu

Construction of Ylaya Flood Control (Upstream) (Phase II), Ylaya, Dumanjug, Cebu is a DPWH-tracked public work in DUMANJUG (CEBU), CEBU, Region VII. Reported contract value: ₱87,812,030.33. Status: Reported complete (DPWH). Contractor on record: QM BUILDERS. Figures trace to sumbong.

DUMANJUG (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mainit River Flood Control Structure, Naga City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 7th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱87,812,030.33

Progress

Reported complete (DPWH)

Start Date

June 27, 2023

Target End

April 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.