Flood Control and Drainage20CB0032

CONSTRUCTION OF MASUAJE RIVER CONTROL (PILAR SECTION), PILAR, BATAAN

CONSTRUCTION OF MASUAJE RIVER CONTROL (PILAR SECTION), PILAR, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱45,206,420.00. Status: Reported complete (DPWH). Contractor on record: BPQ CONST AND TRADING. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20CB0032

₱43,832,110.86 · E.R. VENZON CONSTRUCTION/ BPQ CONSTRUCTION AND TRADING JOINT VENTURE

4. Implementation

Contract Amount

₱45,206,420.00

Progress

Reported complete (DPWH)

Start Date

December 2, 2020

Target End

July 17, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.