Buildings and Facilities16JF0060

CONST./COMPLETION/REHAB OF BUILDINGS AND OTHER STRUCTURES (CLUSTERED) A.) CONST. OF MPB (COVERED COURT) JOHN DONTON ELEM. SCHOOL, BRGY. CONCEPTION, KAB. Z.S B.) CONST. OF MPB (COVERED COURT) BRGY. NEW SAGAY, R.T. LIM Z.S C.) CONST. OF MPB (COVERED COURT)

CONST./COMPLETION/REHAB OF BUILDINGS AND OTHER STRUCTURES (CLUSTERED) A.) CONST. OF MPB (COVERED COURT) JOHN DONTON ELEM. SCHOOL, BRGY. CONCEPTION, KAB. Z.S B.) CONST. OF MPB (COVERED COURT) BRGY. NEW SAGAY, R.T. LIM Z.S C.) CONST. OF MPB (COVERED COURT) is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱5,860,000.00. Status: Reported complete (DPWH). Contractor on record: GJD CONST. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control (Phase III) along Sibuguey River Basin, Barangay Sibuguey, Siay, Zamboanga Sibugay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-17-0019718

₱-8,027,966.00 · FY2017

Released to Negros Occidental Issu 4th District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction/Completion/Rehab of Buildings and Oth

₱5,760,000.00 · GJD CONSTRUCTION & SUPPLY

4. Implementation

Contract Amount

₱5,860,000.00

Progress

Reported complete (DPWH)

Start Date

April 3, 2017

Target End

June 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.