Flood Control and Drainage16OH0006

ROAD AND DRAINAGE IMPROVEMENT,ZONE 91/92 (T.LUIZ CENTRAL HILUM), PANDACAN, MANILA

ROAD AND DRAINAGE IMPROVEMENT,ZONE 91/92 (T.LUIZ CENTRAL HILUM), PANDACAN, MANILA is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱9,074,492.89. Status: Reported complete (DPWH). Contractor on record: C. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

231 projects · ₱6.0B total · 0 flags

4. Implementation

Contract Amount

₱9,074,492.89

Progress

Reported complete (DPWH)

Start Date

March 29, 2016

Target End

July 26, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.