Flood Control and Drainage19IM0014

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF REVETMENT ALONG MANGONBANGON RIVER, TACLOBAN CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF REVETMENT ALONG MANGONBANGON RIVER, TACLOBAN CITY is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱18,618,798.55. Status: Reported complete (DPWH). Contractor on record: B VICENCIO BUILDERS BVB INC FORMERLY:B VICENCIO CONST 9687. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 9687

354 projects · ₱20.8B total · 0 flags

Other projects by this contractor

No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SAN JUANICO BR) - K0810+134 - K0810+500, K0815+000 - K0815+550, K0817+500 - K

Region VIII, Region VIII

2024₱332.5M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITES - CONSTRUCTION OF JUNCTION NATIONAL ROAD BRGY. CAROLINA, CAN-AVID - DOLORES - MASLOG ROAD, (BRGY. MAGSAYSAY - BRGY. MAGONGBONG - BRGY. GAP-A

Region VIII, Region VIII

2022₱238.6M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR

Region VIII, Region VIII

2019₱236.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) K0695+000 - K0696+178, K0697+217 - K0697+533, K0724+748 - K0726+929, SAMAR 1ST

Region VIII, Region VIII

2024₱214.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2024₱192.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPVT. OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS

Region VII, Region VII

2016₱178.0M
Reported complete (DPWH)
View all 354 projects →

4. Implementation

Contract Amount

₱18,618,798.55

Progress

Reported complete (DPWH)

Start Date

June 7, 2019

Target End

October 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.