CONCRETING OF SAN AGUSTIN TO BRGY. SAN PEDRO FMR, BRGY. SAN AGUSTIN AND BRGY. SAN PEDRO, BAUAN, BATANGAS

CONCRETING OF SAN AGUSTIN TO BRGY. SAN PEDRO FMR, BRGY. SAN AGUSTIN AND BRGY. SAN PEDRO, BAUAN, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱19,900,000.00. Status: Reported complete (DPWH). Contractor on record: KERAND BUILDERS AND SUPPLY. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱8,794,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Banoyo, San Luis, Batangas
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Batangas 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

21DE0168 Concreting of San Agustin to Brgy. San Pe

₱19,301,010.00 · KERAND BUILDERS AND SUPPLY

4. Implementation

Contract Amount

₱19,900,000.00

Progress

Reported complete (DPWH)

Start Date

June 16, 2022

Target End

March 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.