Buildings and Facilities17FE0097

CONSTRUCTION OF TWO (2) UNITS FOUR (4) STOREY TWENTY FOUR (24) CLASSROOM SENIOR HIGH SCHOOL BUILDING,(UNDER DEPED CY 2016 BEFF BATCH 11) CAMARINES SUR NATIONAL HIGH SCHOOL (LIBOTON ANNEX) , NAGA CITY,CAMARINES SUR

CONSTRUCTION OF TWO (2) UNITS FOUR (4) STOREY TWENTY FOUR (24) CLASSROOM SENIOR HIGH SCHOOL BUILDING,(UNDER DEPED CY 2016 BEFF BATCH 11) CAMARINES SUR NATIONAL HIGH SCHOOL (LIBOTON ANNEX) , NAGA CITY,CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱102,450,000.00. Status: Reported complete (DPWH). Contractor on record: HGG BUILDERS. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱1,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Brgy. Vinagre, Tigaon, Camarines Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Camarines Sur 3rd DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

233 projects · ₱17.1B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENTRESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG ESTRELLA, STA. 000+000-STA. 000+616.85, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱277.2M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, (UPSTREAM), BRGY. MULAWIN-BRGY. DEL PILAR, NAUJAN,

Region IV-B, Region IV-B

2025₱276.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 22: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- REHAB. OF ROAD WITH SLIPS, SLOPE CIOLLAPSE AND LANDSLIDE ALONG TAYTAY-BANTULAN-STA. CRUZ PORT ROAD, 22.1: STA. 1+026-STA. 1+161 (R/S); 22.2: STA. 1+057-STA. 1+164 (L/S); 22.3: STA.

Region IV-B, Region IV-B

2022₱252.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION SAWANG, RIGHT SIDE PHASE 1, LOBOC,

Region VII, Region VII

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF MOGPOG SHORE PROTECTION/BOULEVARD, MOGPOG, MARINDUQUE

Region IV-B, Region IV-B

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF LIPA-MATAAS NA KAHOY ROAD INCLUDING URBAN DRAINAGE DEVELOPMENT AND ROAD SAFETY DEVICES, BATANGAS

Region IV-A, Region IV-A

2023₱241.2M
Past target date (DPWH On-Going)
View all 233 projects →

4. Implementation

Contract Amount

₱102,450,000.00

Progress

Reported complete (DPWH)

Start Date

October 24, 2017

Target End

November 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.