Construction of Flood Mitigation Structure23MG0015

Construction of River Bank Protection along Safali River, Brgy. Naci, Surallah, South Cotabato

Construction of River Bank Protection along Safali River, Brgy. Naci, Surallah, South Cotabato is a DPWH-tracked public work in SURALLAH (SOUTH COTABATO), SOUTH COTABATO, Region XII. Reported contract value: ₱28,899,987.85. Status: Reported complete (DPWH). Contractor on record: REYDAN BUILDERS. Figures trace to sumbong.

SURALLAH (SOUTH COTABATO), SOUTH COTABATO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kolambog Flood Control/Slope Protection (Sheet Piles) along Cotabato-Marbel Road (Allah River, Kolambog Section), South Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

South Cotabato 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,899,987.85

Progress

Reported complete (DPWH)

Start Date

June 8, 2023

Target End

November 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.