Buildings and Facilities19DH0046

CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. SULIB, PANGIL, LAGUNA

CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. SULIB, PANGIL, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱7,226,818.04. Status: Reported complete (DPWH). Contractor on record: 11 DIAMOND EAGLE CONST CORP FORMERLY:11 DIAMOND EAGLE CONST 33328. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱7,226,818.04

Progress

Reported complete (DPWH)

Start Date

July 8, 2019

Target End

November 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.