Flood Control and Drainage19AC0093

CONST. OF FLOOD CONTROL - CONCRETE REVETMENT WALL ALONG STO. TOMAS - QUIMMARAYAN RIVER, STO. DOMINGO

CONST. OF FLOOD CONTROL - CONCRETE REVETMENT WALL ALONG STO. TOMAS - QUIMMARAYAN RIVER, STO. DOMINGO is a DPWH-tracked public work in Ilocos Sur 1st DEO, Region I. Reported contract value: ₱9,310,021.35. Status: Reported complete (DPWH). Contractor on record: FIT CONST. Figures trace to dpwh.

Ilocos Sur 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,310,021.35

Progress

Reported complete (DPWH)

Start Date

August 2, 2019

Target End

November 14, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.