Bridges19FH0134

CONSTRUCTION OF BANA-BANANON BRIDGE, SOGOD SIMAMLA, VIRAC, CATANDUANES

CONSTRUCTION OF BANA-BANANON BRIDGE, SOGOD SIMAMLA, VIRAC, CATANDUANES is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱19,598,229.18. Status: Reported complete (DPWH). Contractor on record: A V LAYNES TRADING AND CONST. Figures trace to dpwh.

Catanduanes DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-19-0006656

₱25,906,952.00 · FY2019

Released to South Manila District Engineering Offi Batangas Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱19,598,229.18

Progress

Reported complete (DPWH)

Start Date

August 23, 2019

Target End

April 21, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.