Roads22K00126

CONSTRUCTION OF SAN MARTIN ROAD CONNECTING PHIVIDEC INDUSTRIAL SITE, PACKAGE 2, VILLANUEVA, MISAMIS ORIENTAL

CONSTRUCTION OF SAN MARTIN ROAD CONNECTING PHIVIDEC INDUSTRIAL SITE, PACKAGE 2, VILLANUEVA, MISAMIS ORIENTAL is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱65,511,740.84. Status: Reported complete (DPWH). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

357 projects · ₱29.2B total · 0 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱65,511,740.84

Progress

Reported complete (DPWH)

Start Date

April 11, 2022

Target End

February 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.