Roads23JA0032

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES: CONSTRUCTION OF ROAD, BARANGAY DIVISORIA, ZAMBOANGA CITY, ZAMBOANGA DEL SUR

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES: CONSTRUCTION OF ROAD, BARANGAY DIVISORIA, ZAMBOANGA CITY, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱9,893,657.45. Status: Reported complete (DPWH). Contractor on record: KIM JOAN CONST. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Ayala, Zamboanga City, Zamboanga del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga City 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,893,657.45

Progress

Reported complete (DPWH)

Start Date

March 15, 2023

Target End

November 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.