Bridges17PJ0016

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS - CONSTRUCTION OF NEW PERMANENT BRIDGES - PUGO BRIDGE ALONG ALFONSO LISTA - AURORA BOUNDARY ROAD

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS - CONSTRUCTION OF NEW PERMANENT BRIDGES - PUGO BRIDGE ALONG ALFONSO LISTA - AURORA BOUNDARY ROAD is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱32,761,701.14. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱32,761,701.14

Progress

Reported complete (DPWH)

Start Date

November 10, 2017

Target End

June 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.