OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF CASILI CREEK RIVER FLOOD CONTROL PROJECT ALONG PRESIDENT BRIDGE, (MALIGAYA SECTION UPSTREAM), MALL
OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF CASILI CREEK RIVER FLOOD CONTROL PROJECT ALONG PRESIDENT BRIDGE, (MALIGAYA SECTION UPSTREAM), MALL is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱96,489,689.86. Status: Past target date (DPWH On-Going). Contractor on record: JWU CONST AND SUPPLY. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost