Buildings and Facilities24PL0044

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MACUTAY, RIZAL, KALINGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MACUTAY, RIZAL, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱3,955,307.73. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ATM CONST 46199. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Liwan East - Calaocan along Pangol Creek, Sta. 11 + 060 - Sta. 11 + 160, Barangay Liwan East, Calaocan, Arsenio, Rizal, Kalinga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Lower Kalinga DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 46199

13 projects · ₱83.0M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT); MALLANGO - ASAFANG - TABTABAN - SUMA

Upper Kalinga DEO, Cordillera Administrative Region

2024₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT): MALLANGO-ASAFANG-TABTABAN-SUMADEL ROAD

Upper Kalinga DEO, Cordillera Administrative Region

2023₱9.8M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUGNAY, BANGAD CENTRO, MALLANGO, TINGLAYAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2025₱8.4M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES CONSTRUCTION OF ROAD, SAMBO-PUAPO, DALUPA, POBLACION, ASAFANG-TABTAFAN ACCESS ROAD, BARANGAY DANGTALAN, BARANGAY DALU

Upper Kalinga DEO, Cordillera Administrative Region

2025₱8.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ACCESS ROAD TO BULO NATI

Lower Kalinga DEO, Cordillera Administrative Region

2025₱7.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF ROAD, PUROK 4, MAPAOAY (BALIYAO SECTION) ACCESS ROAD, BAR

Lower Kalinga DEO, Cordillera Administrative Region

2025₱5.9M
Reported complete (100% progress, DPWH status On-Going)
View all 13 projects →

4. Implementation

Contract Amount

₱3,955,307.73

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 13, 2024

Target End

September 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.