GAA 2016 MFO-315M00101

ROAD UPGRADING (UNPAVED TO PAVED) OF POBLACION ALAMADA TO SITIO DUALING LEADING TO ASIK-ASIK FALLS, K1687+676.26 - K1689+000; K1693+320 - K1696+580, BRGY. DADO, ALAMADA, NORTH COTABTO

ROAD UPGRADING (UNPAVED TO PAVED) OF POBLACION ALAMADA TO SITIO DUALING LEADING TO ASIK-ASIK FALLS, K1687+676.26 - K1689+000; K1693+320 - K1696+580, BRGY. DADO, ALAMADA, NORTH COTABTO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱137,411,991.20. Status: Reported complete (DPWH). Contractor on record: GEMMA CONST SUPPLY INC FORMERLY:GEMMA CON. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱137,411,991.20

Progress

Reported complete (DPWH)

Start Date

May 11, 2016

Target End

April 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.