Buildings and Facilities20IF0072

CONSTRUCTION OF COVERED COURT, BRGY. SAN DIONISIO, MATAG-OB, LEYTE

CONSTRUCTION OF COVERED COURT, BRGY. SAN DIONISIO, MATAG-OB, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱2,819,711.29. Status: Reported complete (DPWH). Contractor on record: GBTU CONST AND SUPPLIES FOR: K T U CONST. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱15,212,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Miguel Flood Control, Palompon, Leyte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Leyte 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,819,711.29

Progress

Reported complete (DPWH)

Start Date

October 14, 2020

Target End

January 11, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.