Roads21KB0061

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SAYRE HIGHWAY (JCT BUKIDNON-DAVAO CITY ROAD-COTABATO BOUNDARY, K1605+193-K1605+276, K1606+000-K1606+170, DAMULOG, BUKIDNON

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SAYRE HIGHWAY (JCT BUKIDNON-DAVAO CITY ROAD-COTABATO BOUNDARY, K1605+193-K1605+276, K1606+000-K1606+170, DAMULOG, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱1,924,014.11. Status: Reported complete (DPWH). Contractor on record: MAFIL BUILDERS INC. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System - Water Diversion Canal at Downstream Portion of Taganibong Creek, Maramag, Bukidnon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bukidnon 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,924,014.11

Progress

Reported complete (DPWH)

Start Date

September 24, 2021

Target End

November 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.