Buildings and Facilities19EH0107

CONSTRUCTION OF MULTI - PURPOSE BUILDING(COVERED COURT/EVACUATION CENTER), LUSONG, SAN AGUSTIN, ROMBLON

CONSTRUCTION OF MULTI - PURPOSE BUILDING(COVERED COURT/EVACUATION CENTER), LUSONG, SAN AGUSTIN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱3,841,200.00. Status: Reported complete (DPWH). Contractor on record: ATHENA CONST AND DEVELOPMENT. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,841,200.00

Progress

Reported complete (DPWH)

Start Date

August 12, 2019

Target End

December 9, 2019

5. Audit