Roads21JC0012

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, SINDANGAN-LILOY RD - K1930 + 920 - K1931 + 033, K1938 + 730 - K1938 + 742, ZN.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, SINDANGAN-LILOY RD - K1930 + 920 - K1931 + 033, K1938 + 730 - K1938 + 742, ZN. is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: LONG ISLAND BUILDERS. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱4,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Kauswagan, Sergio Osmena, Zamboanga del Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Zamboanga del Norte 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

275 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PULIRAN RIVER, PULIRAN BR. SECTION PACKAGE 2, SIBUCO, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱164.0M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2025₱153.0M
Past target date (DPWH On-Going)

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (DOWNSTREAM), SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 2

Region IX, Region IX

2024₱137.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE, PACKAGE 1

Region IX, Region IX

2024₱128.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ESPLANADE AT SALUG BRIDGE (B00528MN), SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2023₱109.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER, GUTALAC, ZAMBOANGA DEL NORTE (UPSTREAM) STA. 0 + 204 - 0 + 604

Zamboanga del Norte 3rd DEO, Region IX

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
View all 275 projects →

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

August 12, 2021

Target End

March 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.