Roads19DP0003

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA - STA. CRUZ - FAMY ROAD (S01706LZ) K0069 + 469 - K0071 + 760

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA - STA. CRUZ - FAMY ROAD (S01706LZ) K0069 + 469 - K0071 + 760 is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱23,056,940.37. Status: Reported complete (DPWH). Contractor on record: POWER K CONST SUPPLY. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-19-0022270

₱658,472.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

345 projects · ₱6.8B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, DOH REGION IV-A OFFICE, LIPA CITY

Batangas 4th DEO, Region IV-A

2023₱144.1M
Reported complete (DPWH)
No sat.

LOCALLY-FUNDED PROJECTS, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES, CONSTRUCTION OF DEPARTMENT OF HEALTH REGION 4A REGIONAL OFFICE MARAWOY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS CASILE - TAGAYTAY ROAD, PACKAGE C, LAGUNA

Region IV-A, Region IV-A

2024₱118.1M
Ongoing (DPWH-reported)

CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION/IMPROVEMENT OF TRIBUTARY CREEK AS OUTFALL OF THE DETENTION POND AT BRGY. MAMPLASAN LEADING TO CARMONA-BIÑAN RIVER, BIÑAN CITY, LAGUNA

Region IV-A, Region IV-A

2020₱115.7M
Reported complete (DPWH)
No sat.

SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA

Region IV-A, Region IV-A

2025₱111.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA

Region IV-A, Region IV-A

2021₱101.3M
Reported complete (DPWH)
View all 345 projects →

4. Implementation

Contract Amount

₱23,056,940.37

Progress

Reported complete (DPWH)

Start Date

June 26, 2019

Target End

August 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.