Buildings and Facilities16DF0161

CONSTRUCTION OF 4STY 16CL SCHOOL BUILDING AT BACOOR ES, BACOOR CITY

CONSTRUCTION OF 4STY 16CL SCHOOL BUILDING AT BACOOR ES, BACOOR CITY is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱28,614,134.86. Status: Reported complete (DPWH). Contractor on record: HEXAMINDZ CORP FORMERLY:KILUSANG MAGKAIBIG. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,614,134.86

Progress

Reported complete (DPWH)

Start Date

May 31, 2016

Target End

December 26, 2016