Buildings and Facilities18CK0125

CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT CRISTO REY EAST ELEMENTARY SCHOOL, CAPAS, TARLAC

CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT CRISTO REY EAST ELEMENTARY SCHOOL, CAPAS, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱11,259,346.34. Status: Reported complete (DPWH). Contractor on record: R L D GABRIEL BUILDERS 38746. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,259,346.34

Progress

Reported complete (DPWH)

Start Date

July 5, 2018

Target End

December 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.