Roads20K00195

ROAD WIDENING, SAYRE HIGHWAY - K1504+158 - K1504+706, K1506+155 - K1506+382, K1504+706 - K1505+371, BUKIDNON

ROAD WIDENING, SAYRE HIGHWAY - K1504+158 - K1504+706, K1506+155 - K1506+382, K1504+706 - K1505+371, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱45,708,413.36. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱45,708,413.36

Progress

Reported complete (DPWH)

Start Date

December 7, 2020

Target End

January 4, 2022