Buildings and Facilities24OB0149

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY WEST CRAME, SAN JUAN CITY

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY WEST CRAME, SAN JUAN CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱10,402,116.04. Status: Past target date (DPWH On-Going). Contractor on record: 816 EMBER CONST CORP. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,198,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Canumay West Creek, Barangay Canumay West, Valenzuela City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Metro Manila 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,402,116.04

Progress

Past target date (DPWH On-Going)

Start Date

February 12, 2024

Target End

June 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.