Roads19OD0035

CONSTRUCTION/ REHABILITATION OF ROADS AND DRAINAGE ALONG P. JACINTO ROAD CONNECTING TO GENERAL LUIS ROAD, BRGY. 165, CALOOCAN CITY

CONSTRUCTION/ REHABILITATION OF ROADS AND DRAINAGE ALONG P. JACINTO ROAD CONNECTING TO GENERAL LUIS ROAD, BRGY. 165, CALOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱9,407,540.00. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,407,540.00

Progress

Reported complete (DPWH)

Start Date

June 27, 2019

Target End

November 23, 2019

5. Audit