Buildings and Facilities18KG0073

CONSTRUCTION OF 2 STOREY 2 INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) BUILDING AT SULTAIN ALI DIMAPORO MEMORIAL IS,SULTAN NAGA DIMAPORO(KAROMATAN),LANAO DEL NORTE

CONSTRUCTION OF 2 STOREY 2 INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) BUILDING AT SULTAIN ALI DIMAPORO MEMORIAL IS,SULTAN NAGA DIMAPORO(KAROMATAN),LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱9,710,739.48. Status: Reported complete (DPWH). Contractor on record: SAFENUR CONST. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,710,739.48

Progress

Reported complete (DPWH)

Start Date

July 19, 2018

Target End

November 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.