LOCAL PROGRAM; CONST/REPAIR/REHAB/IMPROVEMENT OF VARIOUS INFRA INCLUDING LOCAL PROJECTS;LOCAL ROADS AND BRIDGES;LOCAL BRIDGES, REHAB/IMPROVEMENT OF ANUNAS BRIDGE AT BARANGAY ANUNAS,ANGELES CITY,PAMPANGA is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱21,518,777.91. Status: Reported complete (DPWH). Contractor on record: AL-B DEVELOPMENT CORP. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-19-0017870

₱1,244,000.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

64 projects · ₱1.6B total · 0 flags

Other projects by this contractor

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG ABACAN RIVER, BARANGAY SAPALIBUTAD, ANGELES CITY, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱96.6M
Reported complete (100% progress, DPWH status On-Going)

Construction of Reinforced Concrete Slope Protection Structure along Abacan River, Barangay Pampang, Angeles City, Pampanga

ANGELES CITY (PAMPANGA), PAMPANGA, Region III

2024₱96.5M
Reported complete (DPWH)
No sat.

Construction of Slope Protection Structure along Abacan River, Barangays Malabanas to Anunas, Angeles City, Pampanga

ANGELES CITY (PAMPANGA), PAMPANGA, Region III

2023₱67.5M
Reported complete (DPWH)
No sat.

FLOOF MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN ANGELES CITY, PAMPANGA (PHASE I)

Pampanga 3rd DEO, Region III

2024₱62.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL PROGRAM; CONST/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES;ANGELES CITY TOLL EXIT CONNECTING NLEX AND SCTEX IN SUPPORT OF HANDICRAFT, FURNITURE,MANUFACTURING,HOTEL, IT-IBPM GARMENTS AND TEXTILES IND

Pampanga 3rd DEO, Region III

2020₱57.9M
Reported complete (DPWH)
No sat.

Construction of Reinforced Concrete Slope Protection with Steel Sheet Piles Foundation along Abacan River, Brgy. Tabun to Capaya, Angeles City, Pampanga - Sta. 1+949 - Sta. 2+699

ANGELES CITY (PAMPANGA), PAMPANGA, Region III

2022₱56.0M
Reported complete (DPWH)
View all 64 projects →

4. Implementation

Contract Amount

₱21,518,777.91

Progress

Reported complete (DPWH)

Start Date

August 29, 2019

Target End

March 10, 2020

5. Audit