Buildings and Facilities19ME0087

CONSTRUCTION OF MPB (BARANGAY HALL) BRGY. MAGULING; MAITUM, SARANGANI PROVINCE.

CONSTRUCTION OF MPB (BARANGAY HALL) BRGY. MAGULING; MAITUM, SARANGANI PROVINCE. is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱2,865,638.17. Status: Reported complete (DPWH). Contractor on record: SAREX BUILDERS AND SUPPLY. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,865,638.17

Progress

Reported complete (DPWH)

Start Date

September 3, 2019

Target End

January 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.