Buildings and Facilities22NI0049

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, DPWH SURIGAO DEL SUR 2ND DEO COMPOUND, MANCAROGO, BISLIG CITY, SURIGAO DEL SUR

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, DPWH SURIGAO DEL SUR 2ND DEO COMPOUND, MANCAROGO, BISLIG CITY, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱10,606,401.67. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control structure at Cumawas-Poblacion, Sta. 0+000.00 - Sta. 2+000.00, Bislig City, Surigao del Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Surigao del Sur 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

223 projects · ₱12.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZ

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE ALONG CULASI, BARANGAY PAM

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER, BANTACAN, NEW BATAAN, DAVAO DE ORO

Davao de Oro 2nd DEO, Region XI

2024₱144.7M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PORT BARTON-TDC ROAD SECTION, STA. 017+770-STA. 017+865; STA. 017+914-STA. 017+969; STA. 018+023-STA. 018+244, PALAWAN

Region IV-B, Region IV-B

2022₱144.5M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1398 + 300- K1398 + 600

Misamis Oriental 1st DEO, Region X

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 1

North Manila DEO, National Capital Region

2025₱140.3M
Past target date (DPWH On-Going)
View all 223 projects →

4. Implementation

Contract Amount

₱10,606,401.67

Progress

Reported complete (DPWH)

Start Date

February 17, 2022

Target End

January 22, 2023

5. Audit