Buildings and Facilities19DE0150

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ALANGILAN ELEMENTARY SCHOOL, BARANGAY ALANGILAN, BATANGAS CITY

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ALANGILAN ELEMENTARY SCHOOL, BARANGAY ALANGILAN, BATANGAS CITY is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱7,920,000.00. Status: Reported complete (DPWH). Contractor on record: WESTHOME ENT. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0014483

₱60,000.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱7,920,000.00

Progress

Reported complete (DPWH)

Start Date

August 5, 2019

Target End

February 12, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.