Construction of Flood Mitigation Structure23CE0019

Construction of Flood Control Structure along Talavera River, Barangay San Nicolas, Llanera, Nueva Ecija

Construction of Flood Control Structure along Talavera River, Barangay San Nicolas, Llanera, Nueva Ecija is a DPWH-tracked public work in LLANERA (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱48,995,000.00. Status: Reported complete (DPWH). Contractor on record: ADROIT EJD CONST CORP FORMERLY: ADROIT CONST / DGSARM BUILDERS INC FORMERLY: D G SARMENTA CONST. Figures trace to sumbong.

LLANERA (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Talavera River, Barangay San Nicolas, Llanera, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0024916

₱371,572.00 · FY2023

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,995,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

September 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.