Roads25HD0078

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTL/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG N BACALSO AVENUE (CEBU SOUTH RD) - K0021+070 - K0022+068,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTL/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG N BACALSO AVENUE (CEBU SOUTH RD) - K0021+070 - K0022+068, is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱2,154,920.00. Status: Reported complete (DPWH). Contractor on record: JANUARY BUILDERS. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Naga River (Upstream), Tinaan, City of Naga, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Probable match · 91%

CONCRETING PHASE III-LOWER LIPATA

₱1,997,813.43 · JANUARY BUILDERS

Probable match · 87%

Construction project

₱2,452,162.80 · JANUARY BUILDERS

Contractor

A

254 projects · ₱1.9B total · 3 flags

4. Implementation

Contract Amount

₱2,154,920.00

Progress

Reported complete (DPWH)

Start Date

March 13, 2025

Target End

March 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.