Roads25HB0062

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM -ROLL-IT) - SAN ROQUE TO BAYBAYON ROAD, MABINI, BO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM -ROLL-IT) - SAN ROQUE TO BAYBAYON ROAD, MABINI, BO is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,885,268.26. Status: Reported complete (DPWH). Contractor on record: G U AUDITOR CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Dike, Cahayag CIS, Tubigon, Bohol
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bohol 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,885,268.26

Progress

Reported complete (DPWH)

Start Date

February 25, 2025

Target End

April 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.