Rehabilitation / Major Repair of Flood Control Structure24CK0102

Rehabilitation of Existing Dike along Maet Creek (Left and Right Bank), D/S of Lara Bridge (Phase V), Sta. 3+004.50 - Sta. 3+479.5, La Paz, Tarlac

Rehabilitation of Existing Dike along Maet Creek (Left and Right Bank), D/S of Lara Bridge (Phase V), Sta. 3+004.50 - Sta. 3+479.5, La Paz, Tarlac is a DPWH-tracked public work in LA PAZ (TARLAC), TARLAC, Region III. Reported contract value: ₱96,497,704.17. Status: Reported complete (DPWH). Contractor on record: HIGH ROCK CONST AND SUPPLIES INC / JHI CONST & SUPPLY. Figures trace to sumbong.

LA PAZ (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tarlac River Control ( Right Dike ) , Villa Paz - Dicolor Section, Gerona, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008260

₱1,425,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008262

₱132,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,497,704.17

Progress

Reported complete (DPWH)

Start Date

February 20, 2024

Target End

August 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.